Top Mold and Tool Maker’s award in 2014 and 2015
October 12, 2015MMI Engineered Solutions Honored as One of the 2016 “Michigan 50 Companies to Watch”
March 14, 2016- 35,000 sq. ft.
–Injection Molding & Asm
- Up to 1500 Ton
–Heavy Crane installation, floor construction and utilities set-up to add another approx. 10+ molding machines.
Initial operations will run two shifts per day/5 days per week.
- Our general timeline shows the following:
–Facility move-in: March 1st , 2016
–Begin Distribution of the Silverback Splash Shields April 1st, 2016
–Molding machine/infrastructure installation May, 2016
–Facility certification June, 2016
–Re-PPAP of Navistar product previously PPAP’d from our Saline, MI facility in July, 2016
–Start of Production of all Navistar product, August, 2016
–Begin Production shipment ready September, 2016